Mersey tidal power: Otterspool to Bromborough named as the preferred spot for the barrage

The long-talked-about plan to harness the River Mersey’s tides has taken a real step forward. The Liverpool City Region Combined Authority has named a 1.5-mile stretch of the river between Otterspool on the Liverpool side and Bromborough on the Wirral as its preferred spot for the Mersey Tidal Power Project.

Combined Authority members will be asked to sign off that location, which planners call the preferred alignment corridor, at a meeting on Friday 6 November. If they agree, the scheme moves on to more detailed engineering, environmental and commercial work ahead of an application for a Development Consent Order, the planning permission needed for a project of national importance.

What is the Mersey Tidal Power Project?

The idea is a barrage across the estuary that makes electricity from the difference in water level on either side as the tide comes in and out. The Combined Authority says the Mersey has a tidal range of up to 10 metres, the second biggest in the UK. It says the scheme could produce up to 1 gigawatt of electricity for 120 years, making it the largest tidal range power plant in the world, and create thousands of jobs.

Since January the project has also been planned as a flood defence, to help protect homes and businesses from rising sea levels. The artist’s impression released with the plans shows a walking and cycling route along the top of the barrage.

Metro Mayor Steve Rotheram, who revived the plan in 2017, called the choice of location a major step forward for a project that could be genuinely transformational for the region and the country.

What happens next?

  • 6 November 2026: the Combined Authority votes on the Otterspool to Bromborough corridor. It will also be asked to back a Regulated Asset Base model to fund the project. This lets the developer start recovering some costs while the barrage is being built, the same approach used for some nuclear and water schemes.
  • Late 2027 or early 2028: a second public engagement, when local people can have their say. The first one, in 2024, drew more than 3,000 responses, with 84% in favour of the project.
  • 2030: the expected date for a final investment decision. No building work can start until planning consent is granted and the money is committed.

You can read the Combined Authority’s full announcement on its website. The BBC notes that a Mersey tidal scheme was first floated in 2005 and shelved in 2011 because it wasn’t seen as profitable enough at the time.